The S 7th Avenue, E Hull Street, E Murray Street, and W Johnson Street projects involve the construction of approximately 4,400 linear feet of 8-inch and 4-inch diameter PVC water line. The project also includes replacing approximately 3,075 linear feet of 6-inch diameter sanitary sewer line; reconstruction of approximately 2,100 linear feet of 29-feet and 27-feet wide asphalt road with concrete curb and gutter; reconstruction of 1,850 linear feet of 18-feet and 31-feet wide asphalt roadway.
The E Bullock Street project involves the construction of approximately 575 linear feet of 8-inch and 6-inch diameter PVC waterline The project also includes the construction of 538 linear feet of 8-inch diameter sanitary sewer line; reconstruction of 506 linear feet of 31-foot-wide asphalt road with concrete curb and gutter.
Timeline
Construction began December 2022 and will take approximately 14 months.
Goal
Improve water and sanitary service, improve storm drainage, and replace damaged road surfaces
Contractor
Lynn Vessels Construction