Post Construction & Acceptance
Construction of public infrastructure, including utility main extensions, street creation, public sidewalk construction, etc., is required to be designed by a Professional Engineer. Prior to construction, construction plans for public elements must be submitted to the City for review and approval.
A punch list inspection will be requested and done at substantial completion. Upon receiving the punch list, the developer can begin gathering the Project Close-Out Documentation, including final record drawings in PDF and CAD file, Two-Year Maintenance Bond, Complete Inventory List, and Affidavit of All Bills Paid.
A Letter of Acceptance will be issued after the project has passed Final Inspection and required items have been submitted.
Punch List Walk-Through
- A punch list walk-through is mandatory prior to final inspection
- The punch list inspection should be scheduled once work is 95% completed. All utilities will have been installed, including dry and franchise utilities, and the site will be clean and accessible to inspections.
- Required punch list inspection attendees:
- Developer or Construction Manager/Contractor
- Wet Utilities Contractor
- City Construction Inspector
- City Stormwater Inspector
- City Supervisors from Streets, Signs, Utilities, and other City departments as necessary
- A punch list will be issued to the Developer or Construction Manager/Contractor
- A .pdf set of record drawings will be submitted to the City Construction Inspector at least 2 days prior to the scheduled punch list walk-through.
- If inspectors arrive for the scheduled walk-through and the site is not ready, the required contractors do not attend, or the walk-through otherwise cannot be completed, it will be cancelled and may be subject to a reinspection fee.
Final Inspection and Acceptance
- Upon completion of the punch list work, the Developer or Contractor will schedule a Final inspection with the City Construction Inspector.
- Additional documentation required prior to acceptance includes:
- Final record drawings in PDF
- Final record drawings in CAD with projection and scale factor OR shape file
- Two-Year Maintenance Bond (bond date begins at final acceptance)
- Complete Inventory List
- Affidavit of All Bills Paid
- A Letter of Acceptance will be issued when the project is complete, and all required items have been submitted.