Civil Construction Acceptance

Post Construction & Acceptance

Construction of public infrastructure, including utility main extensions, street creation, public sidewalk construction, etc., is required to be designed by a Professional Engineer. Prior to construction, construction plans for public elements must be submitted to the City for review and approval.

A punch list inspection will be requested and done at substantial completion. Upon receiving the punch list, the developer can begin gathering the Project Close-Out Documentation, including final record drawings in PDF and CAD file, Two-Year Maintenance Bond, Complete Inventory List, and Affidavit of All Bills Paid.

A Letter of Acceptance will be issued after the project has passed Final Inspection and required items have been submitted.

Punch List Walk-Through

  • A punch list walk-through is mandatory prior to final inspection
    • The punch list inspection should be scheduled once work is 95% completed. All utilities will have been installed, including dry and franchise utilities, and the site will be clean and accessible to inspections. 
    • Required punch list inspection attendees:
      • Developer or Construction Manager/Contractor
      • Wet Utilities Contractor
      • City Construction Inspector
      • City Stormwater Inspector
      • City Supervisors from Streets, Signs, Utilities, and other City departments as necessary
    • A punch list will be issued to the Developer or Construction Manager/Contractor 
  • A .pdf set of record drawings will be submitted to the City Construction Inspector at least 2 days prior to the scheduled punch list walk-through. 
  • If inspectors arrive for the scheduled walk-through and the site is not ready, the required contractors do not attend, or the walk-through otherwise cannot be completed, it will be cancelled and may be subject to a reinspection fee. 

Final Inspection and Acceptance

  • Upon completion of the punch list work, the Developer or Contractor will schedule a Final inspection with the City Construction Inspector.
  • Additional documentation required prior to acceptance includes:
    • Final record drawings in PDF 
    • Final record drawings in CAD with projection and scale factor OR shape file
    • Two-Year Maintenance Bond (bond date begins at final acceptance) 
    • Complete Inventory List 
    • Affidavit of All Bills Paid 
  • A Letter of Acceptance will be issued when the project is complete, and all required items have been submitted. 

Relevant Documents:

Final Acceptance Procedures

Affidavit of All Bills Paid

Inventory List

Final Acceptance Application